Kiln commissioning:
1.Before commissioning the foundation level to check whether there are changes around the bolts are tightened to check whether all lubrication points to add a little grease, before using the roller bearing means in the rotary kiln roller axial neck with a layer of oil can be poured oil, check whether there is something stuck in rotating parts, each cooling water pipe is smooth, the entire check the correct order to make a trial run.
2.The whole kiln must first stand-alone commissioning Before commissioning, the motor idling for 2 hours reducer idling 8 hours (4 hours drag by the main motor). Recording current, heated and listen for unusual sounds.
3. Before commissioning brick kiln shell, not less than one day (continuous time). Then asked to make the following checks.
Checking all parts lubrication, whether there is leakage. Temperature, currents, temperature generally should not exceed 30 ℃, motor load should not exceed 15% of rated power.
Checking Abnormal noise whether the transmission of vibration, shock, ring gear and the pinion gear is normal exposure.
Exposure belt and idler wheel is normal, whether the gap between the thrust ring and bracket axle bracket axle bush normal.
Sealing means sealing structure and some blowing means ends the operation of the kiln shell whether it can maintain a good state, not allowed to have a greater leakage gap.
Whether the bolt loosening.
After the commissioning of the brick kiln drying kiln English at the same time, this time do these inspections as followings.
Since kiln weight gain, to check the oil tank temperature does not exceed 35 ℃, bearing temperature rise should not exceed 40 ℃, motor load should not exceed 25% of rated power, special inspections roller adjusted to correct, such as roller and tire the contact surface is uniform and so on. Other inspection items bricklaying examination before the operation.